Grid project Mörel – Ulrichen

A new 380 kilovolt line is being constructed between Mörel and Ulrichen. The construction of this line is necessary to ensure that all of the energy generated from hydropower in the Valais can reach Central Switzerland and Ticino.

Your contact for this grid project

Jan Schenk
Jan Schenk

Phone +41 58 580 21 11
info@swissgrid.ch

380 kV line
380 kV line
220 kV line
220 kV line
Dismantling
Dismantling
Existing line
Existing line
Substation
Substation

Overview

The extra-high-voltage line between Mörel and Ulrichen will be newly constructed with a voltage of 380 kilovolt. Without connecting the transmission lines in the Valais to the 380-kilovolt grid, it will only be possible to transport around two thirds of the Valais production from hydropower once the new Nant de Drance pumped storage power plant commences operation. The construction of the SBB's new 132 kilovolt railway power line is also critical for the secure operation of the New Railway Link through the Alps (NRLA) at the Gotthard.

Improvement compared to the current situation

  • The lines with lower voltage levels and the SBB railway power line will be bundled on the same pylons. This will relieve the burden on Goms.
  • The new line will be built on the shaded southern slope further away from the settlement areas. The existing 220 kilovolt line will be dismantled. This currently passes through the centre of villages, especially in the region of Grengiols, Bister und Ernen, impairing the development of these settlements.
  • All provisions relating to limits for electromagnetic radiation are complied with, while the values in some areas are well below these limits. The noise burden is significantly reduced.
Opinions and impressions of the project
Opinions and impressions of the project

Project

Bitsch/Massaboden – Mörel section

  • The existing 220 kV line between the Elektra Massa power plant in Bitsch and the switchgear in Mörel-Filet will be converted. The valley crossing between the Bitsch substation and Termen with four new pylons has already been constructed. Now, 7 pylons will be replaced to accommodate the 132 kV railway power line, which will also be 8 metres higher. The main pylon and cable installation activities are expected to be carried out in 2024/2025.
  • Swissgrid has renewed the switchgear in Bitsch. Construction started in April 2020 and the project was completed in April 2022.

Mörel – Ernen section

  • The planning approval decision by the Swiss Federal Office of Energy (SFOE) from December 2016 for the construction of the new extra-high-voltage line between Mörel and Ernen is legally binding. The Federal Administrative Court confirmed the overhead line version on 26 March 2019 and rejected the complaints. No complaints were submitted to the federal court by the deadline. Swissgrid had submitted a comprehensive cable study with various cable variants in the area of the Binna crossing.
  • Swissgrid can now construct the new overhead line. The preliminary work will be carried out in 2020. The access paths to the future pylon locations and installation areas will be created until the spring of 2021. The construction of the pylon foundations will take place in the summer and autumn of 2021. The pylons themselves will be installed between 2022 and 2023. Once the pylons have been installed, the next stage between summer 2023 and spring 2024 will be to fit the 18 conductors that will later transport the electricity. The line Mörel – Ulrichen combines a total of four voltage levels: Swissgrid’s 380-kV and 220-kV extra-high-voltage lines, SBB’s 132-kV railway power line and Valgrid’s 65-kV distribution grid line. The green paint on the electricity pylons will be replaced by the definitive colour in the summer of 2024. The green paint is to protect the pylons against corrosion and to better integrate them into the landscape.
  • According to the current project planning, the commissioning of the line section between Mörel-Filet and Ernen will be possible end of 2025 at the earliest, as soon as Valgrid’s new 65-kV substation in Ernen is ready for operation. This means that the dismantling of the existing 220-kV Swissgrid line and the 65-kV Valgrid lines can take place in 2026 at the earliest.
  • Adjustment of the route in Grengiols
    In the municipalities of Grengiols and Bister, five pylons of the originally approved line route will be relocated along a length of approx. 2.3 km. The new line route will require one fewer pylon to be installed, as the geological conditions are more favourable. The relocation of the line has a positive impact on the landscape, and the pylons will be less visible from the village of Grengiols. Following the confirmation of the line route by the Federal Administrative Court in 2019, the canton of Valais reached an agreement with Swissgrid to adjust he line route in the vicinity of the municipality of Grengiols. The project adjustment was legally approved by the Swiss Federal Inspectorate for Heavy Current Installations (ESTI) in March 2021 and can now be implemented.

Schedule for the sub-section between Mörel-Filet and Ernen

Construction of access pathsH2 2020 – H1 2021
ClearingQ3 2020 – Q2 2021
Construction of foundationQ1 2021 – Q4 2022
Installation of pylonsQ4 2021 – Q2 2023
Fitting of conductorsQ2 2023 – Q2 2024
Protection against corrosionQ3 2024
CommissioningQ4 2025
Dismantling of 220 kV and 65 kV linesQ2 2026 – Q3 2026
RecultivationQ2 2022 – Q4 2026

Ernen – Ulrichen section

57 new pylons were built and the existing 220 kilovolt and 65 kilovolt overhead lines will be dismantled between the Ernen and Ulrichen substations. The main work (foundation and pylon construction, rope installation) took place between 2017 and 2020.

  • The foundation was constructed between April and November 2017. Four concrete bases were erected at every pylon location and the foundations were anchored in the subsoil with micropiles. The construction material was transported into the impassable terrain primarily by helicopter, which will result in noise emissions at the construction sites.
  • The installation of the pylons, which are up to 85 metres high, took place between April 2018 and mid 2019. The conductors were installed by the autumn of 2019. The line commenced operating along the Ernen – Ulrichen section in October 2019.
  • By mid-2020, the pylons will be coated in a green paint for protection against corrosion and to better integrate into the landscape. Swissgrid will then return the installation locations to their natural state and restore their ecological value. Swissgrid will also implement national nature conservation projects in the area of the new line route.
  • The existing 220 kV line between Ernen and Ulrichen, which predominantly passes through the villages, was dismantled by mid-2020. This has noticeably reduced the visual impact on the villages of Ernen, Reckingen and Gluringen.

The total costs for the new Mörel – Ulrichen extra-high-voltage line amount to approximately 110 million Swiss francs.

General site plan Ernen – Ulrichen section
General site plan Ernen – Ulrichen section

Dismantling

The existing 220-kilovolt overhead line between Mörel and Ulrichen will be taken down after the new line has been commissioned. The existing 65-kilovolt Mörel – Ernen 1, Mörel – Ernen 2 and Ernen – Ulrichen overhead lines will also be dismantled.

Pylons, conductors, ground conductor and insulators

Steel lattice pylons and plastic insulators will be used for all pylons.

1,000 mm2 Aldrey conductors are used for the transmission and railway power lines; twin conductors will be used in the transmission line. The 65-kilovolt line will be equipped with 600 mm2 Aldrey single conductors. The ground conductor has a diameter of approx. 350 mm2 and contains an integrated fibre-optic cable.

Substation Ernen

A modern 220-kilovolt substation will be built at the new location in Niederernen. The old substation in Fiesch and the line connection will be dismantled. This prevents the crossing of the Rhone and relieves the burden on the settlement area. The centrepiece of the new 220 kV Ernen substation is the gas-insulated switchgear. A second 220/65 kV transformer will also be installed to increase the regional security of supply. Valgrid is building a new 65-kV substation at the Niederernen site.

Meinungen und Eindrücke vom Projekt
Time lapse: New construction of the operations building at the Ernen substation

Mörel substation

Swissgrid is reinforcing the substation in Mörel to increase security of supply. Firstly, a 380-kV gas-insulated switchgear is being built in Mörel. Swissgrid is also installing a new 380/220-kV transformer. Construction will not start until 2025 at the earliest, as it is dependent on the progress of the Chippis – Mörel and Mörel – Ulrichen 380-kV line projects.

Cable study Binna crossing

General site plan cable study Binna crossing
General site plan cable study Binna crossing

A bridge solution to the Binna crossing is being considered for cable version 1. The cable bridge is a version in the topologically difficult area of the Binna crossing with steep drops on both sides.

The cable bridge could be used as a pedestrian connection. Special consideration must be given to the magnetic field on account of the proximity of the pedestrians to the cable arrangement. An aluminium panel could be attached above the cable arrangement to shield the magnetic fields.

Visualisierung Binnaquerung
Visualisation of the Binna crossing cable
Meinungen und Eindrücke vom Projekt
Video: Extra-high voltage line in Goms - construction work is progressing

People & environment

Electromagnetic fields

A total of 19 buildings within the study perimeter were classified as OMEN. The magnetic field was calculated for all OMENs. In 18 OMENs, the system limit value of 1 microtesla was maintained. In one OMEN, the system limit was exceeded slightly – a dispensation has been granted for this.

Landscape

The new line routing is used in the entire project perimeter south of the existing building zones and residential areas. By moving the line from the banks of the Rhône and out of the open agricultural land to the wooded hillsides, the potential conflict of the existing 220 kV line from the construction zones in several communities will be resolved. In terms of the landscape, there will be a general improvement over the existing situation.

Due to the bundling with the 132 kV railway power line and the 65 kV line on the same pylons as well as to the higher voltage, however, the pylons will be taller than the existing 220 kV line.

Forests

The majority of the pylon sites are located in the forest. Other locations are used intensively for agriculture or include semi-dry meadows and extensively grazed areas.

Along the Ernen – Ulrichen section, the clearing work along the line route was carried out in the spring of 2018. This was necessary to ensure safety on the construction site and safe operation of the line. An approximately 30-metre-wide corridor was cleared over a distance of around 16 kilometres. Trees and shrubs are beginning to grow again in this area. Over time, this will allow the line to blend into the landscape better.

A total forested area of 15,288 m2 had to be cleared to install the line at the pylon locations along the Ernen – Ulrichen section. The temporary clearing of 22,572 m2 is required to provide access to the building sites and pylon locations. Suppression is necessary for an area of 292,471 m2.

Grid project Mörel – Ulrichen: Forest-clearing
Grid project Mörel – Ulrichen: Forest-clearing

Natural hazards

After every forest-clearing measure, Swissgrid checks whether additional safety measures are required to protect people and the environment. For example, snow barriers and timber tripods are erected to protect against avalanches. Moreover, Swissgrid also plants young trees in glades along the line route. These kinds of precautions were taken in the municipalities of Ernen, Goms and Obergoms. They guarantee the safety of the roads, which are used year-round, during winter. Besides this, they also support the growth of the forest in the vicinity of the line. The measures allow the forest to fulfil its long-term role of unrestrictedly protecting against avalanches.

In the section stretching from Mörel to Ernen, the forest-clearing activities along the line route are expected to be carried out by the spring of 2021. In this section Swissgrid will once again review whether additional protective measures for avalanches and snow slides are necessary. A definitive assessment of the situation and the agreement upon suitable measures is possible only after deforestation.

Protecting alpine meadows from overgrowth

The construction of the extra-high voltage line will have an impact on nature. By way of compensation, Swissgrid will implement various renaturation projects in the affected municipalities between Mörel-Filet and Ulrichen. For instance, on the Tunetschalp, Swissgrid has created a wet habitat while also contractually assuring that the Tunetschalp and Gorneralp will be regularly maintained over the next 20 years to protect against overgrowth.

As another compensation measure, Swissgrid also intends to protect dry meadows and pastures from overgrowth. A total of seven meadows and pastures will be cleared of overgrowth between Ulrichen and Ernen alone. The associated activities started in autumn 2019 and will last until the end of 2021. The overgrowth in these areas will continue to be managed in the future in order to preserve their ecological value.


Downloads


Grid news

  • | Media release

    A new life for the power cables at the bottom of Lake Lugano

    Read article
  • | Media release

    Temporary voltage increase on the Bickigen – Chippis and Bassecourt – Mühleberg lines

    Read article
  • | Media release

    Groundbreaking ceremony for the new transformer at the Mettlen substation

    Read article

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.