Grid project All'Acqua – Maggia Valley – Magadino

Swissgrid is to build a new power line between All’Acqua in the Bedretto Valley and Magadino. The project was developed in cooperation with authorities and infrastructure managers. The new lines will replace the current ones, which are undersized and nearing the end of their life cycle. Once the other projects in the region have also been completed, it will be possible to remove more than 70 km of power lines, which will lessen the impact on valuable landscapes and residential areas.

Your contact for this grid project

Gabriele Crivelli

Communication Manager
info@swissgrid.ch

Overview

The project, part of Swissgrid’s Strategic Grid 2025, will establish a double connection at 220 kV over a length of approx. 66 km between All’Acqua and Magadino through the Maggia Valley, replacing the current line, which is now old and undersized. The project emerged from a joint study carried out by the Canton of Ticino, Swissgrid, AET and FFS.

Once the new power line has been built and the other projects in the region have been completed, it will be possible to remove more than 70 km of power lines, which will lessen the impact on valuable landscapes. Not only will this benefit the valuable area of Upper Ticino, but it will also increase the transport capacities of the grid at the same time and improve the transportation of energy produced in Vallemaggia, which is currently restricted.

At its meeting on 20 December 2024, the Federal Council defined the geographical area for planning the new lines and chose which technology to use (overhead line or underground cable).

Corridor de planification

Project

The extra-high-voltage lines in the Maggia Valley are crucial for the energy supply of the southern Alps and Switzerland. By implementing the «All'Acqua – Maggia Valley – Magadino» grid project, which is included in its Strategic Grid 2025, Swissgrid is aiming to modernise and upgrade the existing line whilst reducing its impact on the local area and the environment. The project involves replacing the existing 220-kV line with a new double connection at the same voltage

Once the new power line has been built and the other projects in the region have been completed, it will be possible to remove more than 70 km of power lines. The video briefly illustrates the benefits of the project.

The result of cooperation with authorities and infrastructure managers

The project came about as part of the «Studio Generale», a working group that Swissgrid participated in with local partners to find a coordinated solution for power lines and regional planning. See our blog «Power lines and regional planning go hand in hand in Ticino» for more information.

Working together in this way ensures better coordination of planning phases and optimal use of synergies. The Federal Council now intends to implement this model throughout Switzerland in order to speed up approval processes. See our blog «Preparing the grid for the energy transition» for more information.

Ensuring a secure energy supply

The current power lines, built in the 1960s, are undersized and nearing the end of their life cycle. At certain times of the year, the hydroelectric plants in the Maggia Valley have to limit production by almost one third due to insufficient capacity on the transmission lines. Given the current energy situation, restricting renewable energy production in this way is no longer sustainable in the long term. The new power line, consisting of a double connection at 220 kV, solves capacity problems and will help to ensure a secure supply of electricity for Switzerland and Ticino in the future.

Benefits for the landscape and nature

Once the new power line has been built and the other projects in the region have been completed, it will be possible to remove more than 70 km of power lines, which will lessen the impact on valuable landscapes. Improvements are planned in the Bedretto Valley, on the Cristallina pass and in the Alpe Zaria and Campolungo areas, both of which are included in the Federal Inventory of Landscapes and Natural Monuments. Bypassing the beech forests in the Lodano Valley, a UNESCO World Heritage Site, is another benefit of the redevelopment project.

1/2
2/2

Thanks to the current project, it will be possible to remove more than 70 kilometres of overhead lines, which will lessen the impact on the landscape and on residential areas.

Benefits for residents too

The impact on neighbouring villages will also be reduced given that electricity will be transported via underground cables between Cavergno and Lodano and on the slope near Riazzino, whilst pylons will no longer cross the plain between Lodano and Avegno, but will be moved to the right side of the valley. The construction of a new underground tunnel will allow the line that currently runs through the Lavizzara Valley to be dismantled. Swissgrid's future project boasts a total of more than 30 kilometres of underground lines from the All'Acqua substation to the Magadino substation. This is a record on a national scale and represents an important redevelopment for our entire Alpine region.


Next steps

At its meeting on 20 December 2024, the Federal Council defined the geographical area for planning the new lines and chose which technology to use (overhead line or underground cable).

The executive followed the proposal drawn up during the Transmission Lines sectoral plan (PSE) procedure by the support group consisting of cantonal and federal authorities and environmental organisations, which was the result of a careful evaluation of the interests at stake.

The Federal Council’s decision is binding for Swissgrid, which will now define the route of the new lines and acquire the necessary easements. Once the planning stage is complete, the project will be submitted to ESTI for approval. Swissgrid will then be able to organise and contract the work, which is scheduled to start in 2031 at the earliest.

Dialogue with authorities, associations and the population is crucial for Swissgrid. During the planning stage, Swissgrid will set up an advisory commission made up of cantonal and municipal authorities, environmental associations and Swissgrid representatives as it determines the route of the new lines.

The following timeline is based on current planning and presents the best-case scenario, without taking into account any appeals to the courts.

PSE procedure2015–2024
Public consultationAutumn 2023
Federal Council’s decision on corridor and technology20 December 2024
Swissgrid planning2025–2028
Planning approval procedure2028–2031
Construction work on new lines2031–2036
Dismantling of existing lines (as soon as all the projects in Leventina and Vallemaggia are completed)2036–2039

Downloads


Additional information

  • Approval process

    Swissgrid is responsible for the project planning for and implementation of the transmission lines.

    Learn more

  • Grid technologies

    The decision on whether to install a high-voltage line as an overhead line or as an underground cable is based on objective criteria. That's why Swissgrid checks the cable and overhead line options for every grid project.

    Learn more

Grid news

  • | Media release

    A new life for the power cables at the bottom of Lake Lugano

    Read article
  • | Media release

    Temporary voltage increase on the Bickigen – Chippis and Bassecourt – Mühleberg lines

    Read article
  • | Media release

    Groundbreaking ceremony for the new transformer at the Mettlen substation

    Read article

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.